Adaptation of Contracts in Türkiye: Excessive Difficulty (TBK Art. 138), Leases, Currency Debts, Works
Speech is produced by your browser’s own speech engine.
Short answer: Under Turkish law, in cases of excessive difficulty of performance the debtor may ask the court to adapt the contract to the new conditions or, if that is not possible, withdraw from the contract. This applies if an extraordinary situation that the parties did not foresee and could not have been expected to foresee when the contract was concluded arises for a reason not attributable to the debtor, changes the existing facts to the debtor’s detriment to such an extent that demanding performance would be contrary to the rules of good faith, and the debtor has not yet performed or has performed while reserving its rights; in contracts with continuous performance the debtor, as a rule, terminates instead (Code of Obligations art. 138). According to the Court of Cassation Civil General Assembly, all of these conditions must be present together, and if even one of them is missing the contract cannot be adapted. An increase in exchange rates is generally not regarded as sufficient on its own; the sudden and excessive nature of the change, the term of the contract, the party’s profession and whether it has foreign-currency income are assessed together. In leases of residential and roofed business premises, inflation and changes in comparable rents are matters for a rent determination action under Code of Obligations art. 344 and are not, in addition, grounds for adaptation, while in lump-sum works contracts Code of Obligations art. 480/2 provides a separate route to adaptation.
This article explains Turkish law. It is an English translation of the Turkish original; in case of any discrepancy, the Turkish text prevails.
Adaptation of contracts for excessive difficulty of performance under Turkish law: the conditions of Code of Obligations art. 138 (unforeseeability, a cause not attributable to the debtor, an imbalance contrary to good faith, performance not yet rendered or rendered under reservation), adaptation, withdrawal and termination, the distinction from impossibility, the relationship with art. 344 in leases and rent in foreign currency, the foreseeability of exchange-rate increases, art. 480 in works contracts, the competent court, mandatory mediation, proof and verified Court of Cassation decisions.
A guide to the adaptation of contracts under Turkish law: the conditions of excessive difficulty of performance (Code of Obligations art. 138), adaptation by the court, withdrawal and termination, the distinction from impossibility (Code of Obligations art. 136), the good-faith rule (Civil Code art. 2), the relationship with Code of Obligations art. 344 in leases and rent in foreign currency, the foreseeability of exchange-rate increases, adaptation of the lump-sum price in works contracts (Code of Obligations art. 480), the competent court and venue, mandatory mediation, proof and verified Court of Cassation decisions.
What Is Adaptation of a Contract? Pacta Sunt Servanda and Good Faith
The basic principle of contract law is pacta sunt servanda: a contract is performed under the conditions existing when it was concluded. An extraordinary change occurring later may, however, upset the balance between the performances to an unbearable extent for one of the parties. This situation, which legal writing and practice explain through the clausula rebus sic stantibus and the collapse of the foundation of the transaction, is governed as a general rule by Code of Obligations art. 138 under the heading “excessive difficulty of performance”. Re-setting the terms of the contract in line with the changed circumstances is called adaptation of the contract.
The basis of a claim for adaptation is the rule of good faith; according to the Civil General Assembly, the aim is not to set aside the principle of being bound by the contract but to restore contractual justice (Court of Cassation Civil General Assembly, E. 2023/582, K. 2025/24).
“Everyone must comply with the rules of good faith when exercising their rights and performing their obligations. The legal order does not protect the manifest abuse of a right.”
Conditions of Excessive Difficulty of Performance (Code of Obligations art. 138)
According to the Civil General Assembly, all of the following conditions must be present together; if even one is missing, no adaptation is possible, and not every difficulty encountered in the course of performance allows adaptation (Court of Cassation Civil General Assembly, E. 2023/582, K. 2025/24).
“If an extraordinary situation which was not foreseen by the parties and could not have been expected to be foreseen at the time the contract was concluded arises for a reason not attributable to the debtor and changes the facts existing at the time of the contract to the detriment of the debtor to such an extent that demanding performance from the debtor would be contrary to the rules of good faith, and the debtor has not yet performed the obligation or has performed it while reserving the rights arising from the excessive difficulty of performance, the debtor has the right to ask the court to adapt the contract to the new conditions or, where this is not possible, to withdraw from the contract. In contracts involving continuing performance, the debtor, as a rule, exercises the right of termination instead of the right of withdrawal. This article also applies to debts in foreign currency.”
An extraordinary situation that was not foreseen and could not have been expected to be foreseen
The Civil General Assembly links unforeseeability to the foresight expected of an “honest, reasonable and rational” person; the parties’ social status, education and profession, as well as the nature and duration of the contract, are taken into account. Even if the changed circumstances were foreseeable, the condition may be met where their scope, form and consequences could not be predicted and depart substantially from what was foreseeable (Court of Cassation Civil General Assembly, E. 2023/582, K. 2025/24). A debtor who failed to foresee the situation through its own carelessness or inattention cannot rely on the provision (Court of Cassation 13th Civil Chamber, E. 2012/8250, K. 2013/2623). In an upheld judgment it was accepted that the change in economic conditions could not be regarded as unforeseeable for a claimant who is a merchant (Court of Cassation 3rd Civil Chamber, E. 2025/1622, K. 2025/5008).
The situation must not be attributable to the debtor
The event causing the change must not originate from the sphere of control of the party seeking adaptation; that party must also take the necessary measures to prevent the consequences of the change from worsening (Court of Cassation Civil General Assembly, E. 2023/582, K. 2025/24).
An imbalance such that demanding performance would be contrary to good faith
In the words of the Civil General Assembly, the question here is “not whether performance of the obligation is possible, but whether performance can be expected of the debtor” (Court of Cassation Civil General Assembly, E. 2023/582, K. 2025/24). The difficulty need not lead to the debtor’s economic ruin or serious loss, but the position of the other party is also taken into account (Court of Cassation 13th Civil Chamber, E. 2012/8250, K. 2013/2623). Turnover and business-volume data established by expert reports are decisive: in a lease adaptation case brought on pandemic grounds, the first-instance court found no significant decrease in business volume, and the regional court judgment upholding the dismissal was upheld (Court of Cassation 3rd Civil Chamber, E. 2024/1255, K. 2025/813).
The obligation has not been performed, or has been performed under reservation
The debtor may seek adaptation only if it has not yet performed or has performed while reserving its rights arising from the excessive difficulty; it may then reclaim what it performed under the rules on unjust enrichment, depending on the outcome of the adaptation or in the event of withdrawal (Court of Cassation 13th Civil Chamber, E. 2012/8250, K. 2013/2623). Since rent is performed periodically, payment by the tenant without reservation does not bar an action for adaptation (Court of Cassation 3rd Civil Chamber, E. 2018/7863, K. 2019/534). In a construction project progressing through progress payments, by contrast, it was held that adaptation cannot be sought for the parts already covered by progress payments before the request, but that filing the adaptation action itself amounts to a reservation of rights, so performance after the filing date does not bar adaptation (Court of Cassation 6th Civil Chamber, E. 2023/2257, K. 2024/4883).
Adaptation, Withdrawal and Termination; Method of Adaptation
Under Code of Obligations art. 138, the debtor first asks the court for adaptation; if that is not possible it may withdraw from the contract, while in contracts involving continuing performance such as leases it, as a rule, exercises the right of termination instead. In an upheld judgment, the first-instance court stated that when continuing contractual relationships are terminated for just cause, the result arises from a unilateral notice of termination and cannot be achieved by bringing an action (Court of Cassation 3rd Civil Chamber, E. 2024/1255, K. 2025/813).
In adapting a contract, one first looks for an adjustment clause in the contract and then in the law; if an excessive disproportion between the performances has arisen despite an adjustment clause, adaptation is still carried out. Adaptation may take any form the court considers appropriate, such as reducing the burden of performance, increasing the counter-performance, or changing maturities or the manner of performance (Court of Cassation 13th Civil Chamber, E. 2012/8250, K. 2013/2623). The court’s discretion is not unlimited: in ruling on the request, the limit of the relief sought by the claimant must not be exceeded (Court of Cassation 6th Civil Chamber, E. 2023/2257, K. 2024/4883).
Distinction from Impossibility of Performance (Code of Obligations art. 136)
In the case of impossibility, the obligation is extinguished; in bilateral contracts the party released returns what it received under the rules on unjust enrichment and loses the right to claim the performance not yet rendered to it (Code of Obligations art. 136/2). In the case of excessive difficulty, performance is still possible but can no longer be expected of the debtor; the obligation is not extinguished automatically, and the debtor seeks adaptation or, where the conditions are met, withdrawal or termination. The legislative reasoning also characterises excessive difficulty of performance as an institution distinct from impossibility (Court of Cassation 6th Civil Chamber, E. 2023/2257, K. 2024/4883).
“If performance of the obligation becomes impossible for reasons for which the debtor cannot be held responsible, the obligation is extinguished.”
Adaptation of Leases and Code of Obligations art. 344
For the rent in renewed periods of residential and roofed commercial leases, Code of Obligations art. 344 establishes a mandatory regime: agreements on increases are valid provided that they do not exceed the change in the twelve-month averages of the consumer price index in the previous lease year (Code of Obligations art. 344/1); for contracts longer than five years or renewed after five years, and at the end of every five years, the rent is set by the court in accordance with equity (Code of Obligations art. 344/3). Details are discussed in our article on the action for determination of rent.
Grounds for rent determination are not grounds for adaptation. In its decision resolving a conflict between regional courts of appeal, the 3rd Civil Chamber held that inflation, changes in purchasing power, rent inflation and changes in comparable rents are assessed in the action for determination of rent, and that treating them also as grounds for adaptation under Code of Obligations art. 138 would circumvent the mandatory rent-determination procedure. According to the Chamber, the hardship caused by an increase rate that has fallen behind is remedied by the possibility, granted by the Code in the sixth lease year, of setting the rent close to the market rent; nevertheless, if the other conditions of Code of Obligations art. 138 are met, the contractual rent increase rate may also be adapted. The Chamber gave as examples “very sudden and excessive rises and falls in exchange rates, a serious economic crisis shaking the country, earthquake, epidemic, war, coup” (Court of Cassation 3rd Civil Chamber, E. 2026/1213, K. 2026/1751).
Usufructuary lease: In a usufructuary lease where the leased property was neither residential nor roofed commercial premises, the finding that Code of Obligations art. 344 does not apply and that the PPI-linked increase clause binds the parties was upheld (Court of Cassation 3rd Civil Chamber, E. 2025/1622, K. 2025/5008).
Rent in foreign currency: Where the rent is agreed in a foreign currency, no change may be made to it until five years have passed, without prejudice to the legislation on the protection of the value of the Turkish currency; however, the Code additionally reserves the provision on excessive difficulty of performance. Within the first five years, therefore, intervention in foreign-currency rent arises only if the conditions of Code of Obligations art. 138 are met; after five years, the rent is determined under Code of Obligations art. 344/3, also taking into account changes in the value of the foreign currency.
“If the rent has been agreed in a foreign currency in the contract, no change may be made to the rent until five years have passed, without prejudice to the provisions of Law No. 1567 on the Protection of the Value of the Turkish Currency dated 20/2/1930. However, article 138 of this Code entitled “Excessive difficulty of performance” is reserved. In determining the rent after five years have passed, the third paragraph applies, also taking into account changes in the value of the foreign currency.”
Exchange-Rate Increases and Foreseeability
Code of Obligations art. 138/2 expressly provides that the rule also applies to debts in foreign currency. The decisive question is whether the exchange-rate increase was unforeseeable; the decisions put it as follows:
- Foreign-currency-indexed housing loan: The Civil General Assembly held that devaluations are not “something that cannot be predicted in advance”; the reasoning of the Chamber which it endorsed also stressed that the claimant, although a Turkish lira option was available, freely chose a foreign-currency loan and brought the action three years after repayments began (Court of Cassation Civil General Assembly, E. 2014/1614, K. 2014/900).
- Commercial lease in foreign currency: In a lease agreed in euro, the regional court judgment upholding the dismissal was upheld on the ground that “changes in the exchange rate are foreseeable in nature” (Court of Cassation 3rd Civil Chamber, E. 2024/1255, K. 2025/813).
- Objective criteria: The 13th Civil Chamber noted that, in a case concerning a Swiss-franc-indexed loan, foreseeability had been found without explaining the objective criteria relied on and solely by pointing to earlier crises, and reversed the judgment by majority for incomplete examination; the dissent considered that, given the economic crises experienced for years, the element of unforeseeability was not met (Court of Cassation 13th Civil Chamber, E. 2012/8250, K. 2013/2623).
- Long duration and fundamental change: In converting poverty maintenance fixed in foreign currency into Turkish lira, the Civil General Assembly accepted that the conditions for adaptation were met, assessing together the eighteen-year period, the fundamental change in the parties’ circumstances and the fact that the debtor earned no income in foreign currency (Court of Cassation Civil General Assembly, E. 2023/582, K. 2025/24).
According to these decisions, an exchange-rate increase alone is not considered sufficient; the sudden and excessive nature of the change, whether it departs substantially from what was foreseeable, the duration of the contract, the party’s profession and whether it has income in foreign currency are assessed together.
Adaptation of the Lump-Sum Price in Works Contracts (Code of Obligations art. 480)
Under a lump-sum price, the contractor cannot ask for an increase even if the work requires more labour and expense than foreseen; Code of Obligations art. 480/2 creates an exception for circumstances that were unforeseeable at the outset or foreseeable but not taken into account by the parties.
“If the price has been fixed as a lump sum, the contractor is obliged to produce the work for that price. Even if the work required more labour and expense than foreseen, the contractor may not ask for an increase of the price fixed. However, if circumstances that could not be foreseen at the outset, or that could have been foreseen but were not taken into account by the parties, prevent the work from being produced for the lump-sum price fixed by the parties or make it extremely difficult, the contractor has the right to ask the court to adapt the contract to the new conditions or, where this is not possible or cannot be expected of the other party, to withdraw from the contract. Where the rules of good faith so require, the contractor may only exercise the right of termination.”
The 6th Civil Chamber treated Code of Obligations art. 480/2 as one of the special adaptation provisions alongside the general rule in Code of Obligations art. 138; in a lump-sum public construction contract progressing through progress payments, it required the court to assess whether the administration had properly exercised its discretion in rejecting the contractor’s application for termination and liquidation under Law No. 4735 provisional art. 4 and, if not, to examine the conditions for adaptation of the work performed after the filing date, if necessary with an expert report (Court of Cassation 6th Civil Chamber, E. 2023/2257, K. 2024/4883). A construction contract in return for flats (kat karşılığı), however, is not a lump-sum contract, so according to the Chamber it is assessed under Code of Obligations art. 138 rather than Code of Obligations art. 480; in that case the dismissal for failure to prove the conditions for adaptation was upheld as corrected (Court of Cassation 6th Civil Chamber, E. 2024/1956, K. 2025/566).
Competent Court, Venue and Mediation
Subject-matter jurisdiction: In adaptation actions arising from a lease relationship, the civil court of peace has jurisdiction regardless of the value or amount in dispute (Code of Civil Procedure art. 4/1-a); in the lease decisions cited, including the usufructuary lease, the first-instance court was a civil court of peace. For other contracts, unless otherwise provided, the civil court of first instance has jurisdiction (Code of Civil Procedure art. 2/1); special jurisdiction rules for commercial cases or consumer transactions must be considered separately. Accordingly, the works-contract cases cited were heard by civil courts of first instance, while the foreign-currency-indexed housing loan case examined by the Civil General Assembly was heard by a court acting as a consumer court (Court of Cassation Civil General Assembly, E. 2014/1614, K. 2014/900).
“(1) Civil courts of peace, regardless of the value or amount in dispute, hear: a) actions concerning all disputes arising from a lease relationship, including actions for receivables arising from the lease relationship, excluding the provisions on the eviction of leased immovables through enforcement without judgment under the Enforcement and Bankruptcy Law No. 2004 dated 9/6/1932, and actions brought against such actions, …”
Venue: The court of general venue is the court of the defendant’s domicile on the date the action is filed (Code of Civil Procedure art. 6); actions arising from contracts may also be brought before the court of the place where the contract is to be performed (Code of Civil Procedure art. 10).
Mandatory mediation: In disputes arising from a lease relationship, except for the provisions on eviction through enforcement without judgment, applying to a mediator before filing suit is a precondition to suit (Law No. 6325 art. 18/B); an action filed without applying to a mediator is dismissed on procedural grounds for lack of a precondition to suit (Law No. 6325 art. 18/A).
“(1) In the following disputes, applying to a mediator before filing suit is a precondition to suit: a) Disputes arising from a lease relationship, excluding the provisions on the eviction of leased immovables through enforcement without judgment under Law No. 2004.”
Proof and Expert Examination
Unless the law provides otherwise, each party must prove the existence of the facts on which it bases its right (Civil Code art. 6). The party seeking adaptation must prove the extraordinary situation, that it was not attributable to that party, that the balance was upset to an extent contrary to good faith, and that it has not yet performed or has performed under reservation of its rights. Proving that it did not foresee the situation is not enough; the situation must be one that “could not be expected to be foreseen” by it, and the court is obliged to investigate the conditions for adaptation and, where necessary, obtain the opinion of expert witnesses (Court of Cassation 13th Civil Chamber, E. 2012/8250, K. 2013/2623). The main evidence comprises expert reports based on economic data and indices, business data such as turnover and business volume, notices showing that rights were reserved, payment records made under reservation and, in construction works, progress-payment records.
Court of Cassation Decisions
The 13th Civil Chamber decision dates from 2013 and concerns a foreign-currency-indexed housing loan; recent decisions show that lease disputes are reviewed by the 3rd Civil Chamber and works-contract disputes by the 6th Civil Chamber.
The conditions of adaptation are required together; unforeseeability is also assessed in terms of consequences
“All of these conditions required for adaptation of the contract must be present together. In other words, if even one of the conditions set out in article 138 of Law No. 6098 is absent, adaptation of the contract will not be possible. … in determining unforeseeability, not only the likelihood of the changed circumstances arising should be taken into account; even if the changed circumstances were foreseeable, their scope, form and consequences must be unpredictable in nature. … for unforeseeability to produce legal effect, the unforeseen situation must have departed substantially from the foreseeable situation.” (translation)
Rent is a periodic performance: payment without reservation does not bar an action for adaptation
“Rent is among the obligations performed periodically, and the obligation does not end with a single performance. The fact that the tenant claimant made payments without reserving its rights arising from excessive difficulty of performance does not bar its right to bring an action for adaptation.” (translation)
Method of adaptation and the court’s duty to investigate
“Where these conditions are met under article 138 of the Code of Obligations, adaptation must first be requested from the court. Adaptation may be made by reducing the burden of performance or increasing the counter-performance, as well as in any manner the court finds appropriate, such as changing maturities or the manner of performance. The court may also adapt in a manner not envisaged in the claimant’s request. … the court is obliged to investigate whether these conditions exist and, where necessary, must conduct an expert examination and obtain the opinion of expert witnesses.” (translation)
Grounds for rent determination are not grounds for adaptation; the increase rate may be adapted if the conditions of art. 138 are met
“that, in residential and roofed commercial lease contracts, the grounds of the action for determination of rent regulated in article 344 of Law No. 6098 do not constitute the grounds and subject of an action for adaptation of the contract to new conditions due to excessive difficulty of performance regulated in article 138 of the same Law, whereas if the other grounds and conditions in article 138 are met, the rent increase rate set in the contract may be the subject of an action for adaptation” (translation)
Devaluation held foreseeable in a foreign-currency-indexed loan
“It is a fact that devaluations are not something that cannot be predicted in advance for our country and that exchange-rate policies may change at any moment. It is known that devaluations and economic crises do not occur suddenly but arise after certain economic bottlenecks in the market. … The unstable economic situation in our country is something the claimant could predict. In the specific case, the element of unforeseeability, which is one of the conditions for adaptation, did not arise.” (translation)
Even if the event itself was foreseeable, the first condition of adaptation may be met where its consequences were not
“Moreover, the extraordinary circumstance that arises later must have affected the whole of society or a certain part of it. Events affecting only a few debtors are not sufficient for adaptation of the contract. … the claimant’s foreseeing that the Yavuz Sultan Selim Bridge might open in the near future does not mean that it could also foresee that, after the bridge opened, UKOME would oblige certain vehicles to cross the new bridge, or what the tolls of the new bridge and motorway would be. As stated above, there is here an unforeseeability as to the consequences of a foreseeable matter, and the unforeseeability differs substantially from the foreseeable situation.” (unofficial translation)
In the case, a contractor that had concluded a twelve-month transport contract with a public administration on 29.04.2016 had priced its bid on the assumption that its vehicles would use the existing bridge. A UKOME (metropolitan transport coordination centre) decision of 19.08.2016, adopted after the contract, required these vehicles to use the newly opened Yavuz Sultan Selim Bridge; the contractor sought adaptation under art. 138 of the Code of Obligations for the higher tolls and distance costs. The regional court of appeal dismissed the action, holding that the claimant, a merchant, should have foreseen the opening of the bridge and the routing of commercial vehicles to it, and insisted against the reversal of the 11th Civil Chamber. The Assembly held that the claimant, long active in the sector, ought to have foreseen that the bridge would soon open but could not be expected to foresee the compulsory routing and the tolls, and accepted that the first condition of adaptation was met. The insistence judgment was reversed by majority on the grounds stated in the Chamber’s reversal so that the other conditions could be examined. Two dissents considered that, given a merchant’s duty to act as a prudent businessperson (Commercial Code art. 18/2), the opening of the bridge and the routing of commercial vehicles were foreseeable; the first dissent also noted that road and bridge tolls were included in the contract price and that the claimant continued performing without applying to the administration or making a reservation. The Assembly did not order adaptation; the other conditions, such as whether the balance was upset to a degree contrary to good faith, are to be examined anew.
In a paid mining permit on forest land, local opposition is a foreseeable risk; excessive difficulty of performance was not accepted
“…the actual use having been prevented by the villagers’ actions cannot in itself be accepted as a circumstance removing the defendant’s obligation to pay the permit fee. … it was concluded that the defendant had no obligation towards the claimant to explore for minerals or set up facilities at the site and therefore could not plead that these acts could not be carried out because of excessive difficulty of performance, and moreover, since it could be known that in such administrative permits the reaction of local people is a foreseeable risk, the conditions of Article 138 of the Code of Obligations were not met in the specific case.” (unofficial translation)
In the case, the defendant had obtained a paid permit, valid until 10.07.2023, under art. 16 of the Forest Law to explore and operate a mine in a state forest; it paid the first year’s fee, did not pay the following years’ fees on the ground that villagers’ actions prevented it from using the site, and applied for cancellation of the permit in 2017. In its insistence judgment, the first-instance court treated the villagers’ actions as excessive difficulty of performance under art. 138 of the Code of Obligations. The Assembly held that, according to the handover record and undertaking signed by the defendant, the site had been legally and actually handed over; that the defendant could have relinquished the permit in writing and escaped the following years’ fees but did so only after a long time; and that this defence was incompatible with the principles in arts. 2, 3 and 4 of the Civil Code. It therefore held the defendant liable for the fees until the permit was cancelled. The insistence judgment was reversed by majority on the grounds stated in the 3rd Civil Chamber’s reversal. During deliberations, the view that the judgment should be upheld because the defendant never actually benefited from the site was not adopted by the majority. The decision concerns a paid permit granted by the public administration for forest land; it should not be generalised to mean that local opposition is foreseeable in every contract.
Frequently Asked Questions
Under what conditions can adaptation of a contract be requested?
Under Code of Obligations art. 138, an extraordinary situation that was not foreseen and could not have been expected to be foreseen when the contract was concluded must arise for a reason not attributable to the debtor, must change the circumstances to the debtor’s detriment to such an extent that demanding performance would be contrary to good faith, and the debtor must not yet have performed or must have performed under reservation of its rights. All conditions are required together.
Is an increase in the exchange rate sufficient for adaptation of a contract?
On its own it is generally not considered sufficient. The Court of Cassation has treated exchange-rate changes as foreseeable in a foreign-currency-indexed housing loan and in a commercial lease in euro (Court of Cassation Civil General Assembly, E. 2014/1614, K. 2014/900; Court of Cassation 3rd Civil Chamber, E. 2024/1255, K. 2025/813). Where a long period, a fundamental change in the parties’ circumstances and the debtor’s lack of foreign-currency income coincide, however, adaptation may be accepted (Court of Cassation Civil General Assembly, E. 2023/582, K. 2025/24).
The rent has fallen behind; can an action for adaptation be brought instead of an action for determination of rent?
In residential and roofed commercial leases, inflation, rent inflation and changes in comparable rents are the subject of the action for determination of rent under Code of Obligations art. 344 and are not separately grounds for adaptation under Code of Obligations art. 138. If the conditions of Code of Obligations art. 138 are met, the contractual rent increase rate may be the subject of an action for adaptation (Court of Cassation 3rd Civil Chamber, E. 2026/1213, K. 2026/1751).
I paid the rent without any reservation; can I still request adaptation?
Since rent is performed periodically, payment without reservation of rights does not bar an action for adaptation (Court of Cassation 3rd Civil Chamber, E. 2018/7863, K. 2019/534), although the other conditions must also be met. For obligations performed in a single act, adaptation after performance can, as a rule, be requested only if rights were reserved.
Which court hears an adaptation action, and is mediation mandatory?
The civil court of peace has jurisdiction over actions arising from a lease relationship (Code of Civil Procedure art. 4/1-a) and, for other contracts, unless otherwise provided, the civil court of first instance (Code of Civil Procedure art. 2/1); besides the court of the defendant’s domicile, the court of the place of performance also has venue (Code of Civil Procedure art. 10). In lease disputes, applying to a mediator before filing suit is a precondition to suit (Law No. 6325 art. 18/B).
Can a contractor ask for an increase of a lump-sum price in a works contract?
As a rule, no (Code of Obligations art. 480/1). However, if circumstances that could not be foreseen at the outset, or that could have been foreseen but were not taken into account by the parties, prevent the work from being produced for that price or make it extremely difficult, the contractor may ask the court for adaptation or, where this is not possible, withdraw (Code of Obligations art. 480/2).
Disputes concerning adaptation, withdrawal and termination in leases, works contracts and other contracts fall within the firm’s Contract Law practice area.
- Action for Determination of Rent: The Increase Ceiling (CPI Limit), Equity After Five Years, Time to Sue, and the Competent Court
- Defective Delivery in a Turnkey (Works) Contract
- Eviction of Leased Property: Terminating a Lease for Default, Need, a Written Undertaking to Vacate and Two Justified Warnings
- The Legal Nature of Artist Contracts and Withdrawal: Management, Concert, Album and Advertising Agreements under Turkish Law
Related Articles
- Action for Determination of Rent: The Increase Ceiling (CPI Limit), Equity After Five Years, Time to Sue, and the Competent Court
- Defective Delivery in a Turnkey (Works) Contract
- Eviction of Leased Property: Terminating a Lease for Default, Need, a Written Undertaking to Vacate and Two Justified Warnings
- The Legal Nature of Artist Contracts and the Right of Withdrawal: Management, Concert, Album and Advertising Agreements (Code of Obligations arts. 484 and 512, Law No. 5846 art. 58)
This article is for general information purposes only and does not constitute legal advice. Statutory texts are taken from the Official Legislation Information System and decisions from the official case-law database. The decisions cited are not cases handled by the firm.
Author: Contract law attorney Bayram Can Çapar, Denizli, Türkiye - ÇAPAR HUKUK
If you have a question on this topic
This article was written by Av. Bayram Can Çapar. At Av. Bayram Can Çapar · ÇAPAR Hukuk, we provide legal services with our team in Denizli, İzmir, Aydın, Muğla, Manisa, Uşak, Afyonkarahisar, Kütahya, İstanbul and Ankara, Türkiye.
Other articles in Contract Law
- Seller at Gross Fault Loses 2-Year Defect Limitation: Turkish Court of Cassation Assembly of Civil Chambers
- Agency (Mandate) Contract and Revocation of Authority
- Limitation vs Preclusive Periods in Turkish Law: General and Five-Year Periods, Suspension and Interruption
- Turnkey Home Purchases in Türkiye: Off-Plan Sale Contracts, Late Delivery, Withdrawal and Title
Cite as: Av. Bayram Can Çapar, “Adaptation of Contracts in Türkiye: Excessive Difficulty (TBK Art. 138), Leases, Currency Debts, Works”, ÇAPAR Hukuk, 2026-11-19, https://capar.av.tr/en/article/adaptation-contracts