Short answer: “Turnkey” is not a contract type defined by Turkish law; it means the home will be delivered ready to live in. Where a home is bought from a seller acting for commercial purposes and the price is paid before delivery, the contract is a pre-paid home sale (Law No. 6502 art. 40). It must be registered at the land registry or drawn up by a notary in official form; otherwise the seller cannot invoke its invalidity against the consumer (art. 41). The consumer may withdraw without reason within fourteen days, and Law No. 6502 art. 45 also grants a right of rescission for up to twenty-four months from the contract date, subject to deductions. The home must be delivered within forty-eight months at the latest (art. 44). According to the 3rd Civil Chamber, a penalty cumulative with performance and lost rent cannot be claimed together; loss exceeding the penalty may be claimed if the seller’s fault is proved. Mediation must be attempted first for monetary claims, but not for an action for annulment of title and registration.

This article explains Turkish law. It is an English translation of the Turkish original; in case of any discrepancy, the Turkish text prevails.

In brief

Under Turkish law: when buying a turnkey home from a developer, the form of a pre-paid home sale, who may invoke its invalidity, the forty-eight-month delivery limit, penalty clauses and lost rent for late delivery, withdrawal and rescission, security for payments, linked loans, registration and the competent court, with decisions of the Court of Cassation.

Under Turkish law: the type and form of the contract when buying a “turnkey” home from a developer or seller, the delivery period, damages and penalties for late delivery, withdrawal and rescission, security for payments, transfer of title and the competent court.

What Is a Turnkey Home Sale and Which Contract Applies?

“Turnkey” is a commercial expression meaning the home will be handed over with all works finished and ready for occupation. Which rules apply depends on the obligations undertaken and the parties’ capacity, not on the label:

  • Sale of a completed home: the home is transferred by a sale at the land registry; this is a sale of real estate.
  • Sale off-plan or from a building under construction: the price is paid first and the home delivered later. If the seller acts for commercial purposes and the buyer is a consumer, this is a pre-paid home sale under Law No. 6502. A title such as “promise to sell and construction contract” does not change the outcome.
  • Having a home built on one’s own land: this is a works contract (Code of Obligations art. 470 et seq.); see defective delivery in a turnkey works contract. For flat-for-land construction see contractor delay in flat-for-land construction.

This article focuses on the second situation.

Statutory Provision — Law on Consumer Protection (Law No. 6502) art. 40(1) (Pre-paid home sale contracts) (unofficial translation)

“A pre-paid home sale contract is a contract under which the consumer undertakes to pay the sale price of real estate intended as a home in advance, in cash or in instalments, and the seller undertakes to transfer or deliver the real estate to the consumer after the price has been paid in full or in part.”

Consumer and Non-Consumer Home Sales

The Law on Consumer Protection applies only to consumer transactions: the seller must act for commercial or professional purposes and the buyer for non-commercial, non-professional purposes. A person buying a flat to live in from a company running a housing project is a typical consumer. In a sale between two individuals with no commercial purpose, form, defects and damages are assessed under the general provisions of the Turkish Code of Obligations.

The 6th Civil Chamber of the Court of Cassation has held that a landowner who will receive several independent units in exchange for land is not a consumer and that these disputes are heard by the general civil court. In the same decision, the owner of a residential unit in a building undergoing urban transformation as a risky structure was held to be a consumer.

Form: Land Registry, Notary and Simple Written Contracts

Statutory Provision — Law on Consumer Protection (Law No. 6502) art. 41 (Formal requirement) (unofficial translation)

A pre-paid home sale must be registered in the land register, and a promise to sell must be drawn up by a notary in official form. Otherwise the seller may not subsequently invoke the invalidity of the contract to the detriment of the consumer.

… Unless a valid contract has been made, the seller may not ask the consumer to make any payment under any name or to give any document placing the consumer under an obligation.

The Regulation on Pre-Paid Home Sales (art. 6) also allows the contract to be concluded as a written contract made together with registration of the condominium servitude in the consumer’s name. In practice these contracts are often signed as simple written contracts at the sales office. According to the Assembly of Civil Chambers of the Court of Cassation, only the consumer may then rely on the lack of form; the seller cannot escape its obligations by arguing that the contract was not made before a notary.

Where the buyer is not a consumer or the seller has no commercial purpose, this special rule does not apply; official form is the general rule (Code of Obligations art. 237). The consequences of a promise to sell not made before a notary are explained in the article on promises to sell real estate and informal sales.

Pre-Contract Information, Building Permit and Security for Payments

The seller must give a pre-contract information form at least one day before the contract (art. 40(2)). Under the Regulation, the form states the block, parcel, building and floor details, net and gross area, sale price including taxes, withdrawal and rescission rights, delivery date, security arrangement and building permit date; the unit plan and specification list are attached. The seller must prove that the information was given. No contract may be made before the building permit is obtained (art. 40(3)). The contractual default-interest rate may not exceed the contract interest rate by more than thirty per cent (Regulation art. 7).

Regulatory Provision — Regulation on Pre-Paid Home Sales art. 12(1) (Guarantee) (unofficial translation)

Before starting home sales, for projects with thirty or more homes, the seller must take out building completion insurance or provide at least one of the other guarantees and conditions set out below:

a) Bank letter of guarantee,

b) Progress-payment system,

c) Guarantee through a linked loan.

Under a bank letter, if the seller fails to deliver, the consumer claims the price paid from the bank. Under the progress-payment system, payments are held in a blocked account and released in line with construction progress; the unreleased part is returned to the consumer if delivery fails. Compensation under building completion insurance cannot be attached (Regulation arts. 13–15).

Delivery Period and Late Delivery

Statutory Provision — Law on Consumer Protection (Law No. 6502) art. 44 (Delivery of the home) (unofficial translation)

“The pre-paid home must be delivered to the consumer within the period undertaken in the contract. In any event this period may not exceed forty-eight months from the date of the contract. Where the condominium servitude is registered in the land register in the consumer’s name and possession is transferred, transfer and delivery are also deemed to have taken place.”

The provision was amended by Law No. 7392 and its counterpart in the Regulation (art. 10(1)) entered into force on 1 October 2022. A contract is governed by the Regulation as in force when it was made (provisional art. 1); for an older contract, the text in force at that time should be checked.

If the seller does not deliver on the agreed date, it is in default. Buyers usually claim lost rent and the contractual late-delivery penalty. According to the 3rd Civil Chamber of the Court of Cassation:

  • A penalty agreed for late delivery is cumulative with performance and may be claimed together with the home (Code of Obligations art. 179(2)).
  • The penalty and compensation for lost rent cannot be claimed together; if the loss exceeds the penalty, the excess may be claimed only if the seller’s fault is proved (art. 180).
  • The right to the penalty must be reserved by contract or by notice before delivery. A formal notice demanding the penalty sent before delivery was treated as a reservation of rights.

Withdrawal and Rescission

Statutory Provision — Law on Consumer Protection (Law No. 6502) art. 43(1) (Right of withdrawal) (unofficial translation)

“The consumer has the right to withdraw from the pre-paid home sale contract within fourteen days without giving any reason and without paying a penalty. It is sufficient that notice of withdrawal is sent to the seller within this period. The seller must prove that the consumer was informed of the right of withdrawal.”

Under the Regulation, the period runs from conclusion of the contract, notice through a notary suffices and the seller refunds within fourteen days (art. 8). After the withdrawal period there is a separate right of rescission:

Regulatory Provision — Regulation on Pre-Paid Home Sales art. 9 (Rescission of the contract) (unofficial translation)

In a pre-paid home sale, the consumer has the right to rescind the contract without giving any reason for up to twenty-four months from the date of the contract, without prejudice to the rights under article 8 of this Regulation.

… Where the contract is rescinded, the seller may claim the costs arising from taxes, fees and similar statutory obligations incurred because of the sale or promise to sell, and compensation of up to two per cent of the contract price for the first three months from the contract date, up to four per cent for three to six months, up to six per cent for six to twelve months and up to eight per cent for twelve to twenty-four months.

The seller refunds within one hundred and eighty days of the rescission notice. Until transfer or delivery, rescission is free of deductions where the seller fails to perform properly, the consumer dies, permanent loss of earnings leaves the consumer unable to make the pre-payments or leads the seller to reject an ordinary instalment-sale proposal, or the home has been sold to more than one consumer. A consumer who refuses a project change may rescind free of charge within one month; if the change results from a legal requirement or force majeure, the seller may apply the art. 9(3) deductions (arts. 9, 11). The right and these rates also appear in art. 45 of the Law; the Regulation was aligned on 11.3.2017.

The Bank’s Liability When the Home Is Bought with a Loan

Statutory Provision — Law on Consumer Protection (Law No. 6502) art. 35(2) (Linked loans) (unofficial translation)

“In linked loans, where the consumer exercises one of the optional rights set out in article 11 of this Law because the home has not been delivered at all or properly, the seller and the housing finance institution are jointly and severally liable. However, the liability of the housing finance institution is one year, limited to the amount of the loan used, running from the delivery date stated in the home sale contract or the linked loan contract if the home is not delivered, and from the date of delivery if the home is delivered.”

A loan from a bank with no arrangement with the seller, used for a home of the consumer’s own choosing, is not a linked loan (art. 35(4)).

Defective Homes and Price Increase Claims

Statutory Provision — Law on Consumer Protection (Law No. 6502) art. 12 (Limitation) (unofficial translation)

Unless a longer period is set by law or by the contract between the parties, liability for defective goods is subject to a two-year limitation period from the date of delivery of the goods to the consumer, even if the defect appears later. For homes or real estate intended for holiday use, this period is five years from the date of delivery of the real estate.

… If the defect has been concealed through gross negligence or fraud, the limitation provisions do not apply.

Recording defects in the handover report makes proof easier. For a home built under a works contract, notice of defects and time limits follow the Code of Obligations (see the turnkey works contract).

Price increases. The agreed price does not change without agreement or a court decision adapting the contract; an additional price based on rising costs can be sought only under the conditions of excessive difficulty of performance (Code of Obligations art. 138; see adaptation of contracts). Under a works contract with a lump-sum price, the contractor may not ask for an increase because the work required more labour and expense; if unforeseeable circumstances make the work extremely difficult, it may ask the judge to adapt the contract (Code of Obligations art. 480).

If Title Is Not Transferred: Registration Action

If the seller does not transfer title, the consumer may bring an action for annulment of title and registration; any unpaid price is deposited. The Assembly of Civil Chambers has accepted that the consumer may claim registration even under a pre-paid sale made in simple written form, and that the dispute is resolved under Law No. 6502 rather than under the informal-sale conditions of the unification-of-case-law decision of 30.09.1988. In the same case the 7th Civil Chamber had applied the criteria of that decision; the Assembly shared the outcome (simulation must be examined) but changed the reasoning. The decision was taken by majority; the minority considered art. 41(1) inapplicable because the seller had not invoked invalidity.

If the seller transferred the home to another person before the action, a third party who relied on the register in good faith is protected (Civil Code art. 1023); if the transfer was simulated or made knowingly to the consumer’s detriment, the consumer may assert the right against the registered owner as well (see good-faith third parties in title annulment actions). If registration is impossible, the consumer claims a refund or damages; the 3rd Civil Chamber, in a review limited to the grounds of appeal, upheld a judgment calculating the amount paid by reference to the value of a similar home. For buyers of units allotted to the contractor in flat-for-land projects, see good-faith buyers from the contractor.

Competent Court and Mediation

Consumer courts hear actions arising from consumer transactions; the action may also be filed at the consumer’s place of residence (Law No. 6502 art. 73(1), 73(5)).

Statutory Provision — Law on Consumer Protection (Law No. 6502) art. 73/A(1) (Mediation as a precondition to suit) (unofficial translation)

In disputes heard by consumer courts, applying to a mediator before filing the action is a precondition to suit. However, the provisions on mediation as a precondition to suit do not apply to the following matters:

a) Disputes within the jurisdiction of the consumer arbitration committee

… d) Disputes that are consumer transactions and arise from rights in rem over real estate

For late-delivery damages, penalties or refunds, mediation comes first; for annulment of title and registration it is not required. On the arbitration committee’s jurisdiction, see applying to the consumer arbitration committee. Non-consumer sales are litigated before the general courts. In the decisions cited here, refund and damages claims were reviewed by the 3rd, registration against a developer by the 7th, and jurisdiction in flat-for-land construction by the 6th Civil Chamber; the current division of work should be checked on appeal.

Turnkey Home Sales in Court Decisions

In the Assembly of Civil Chambers case, the consumer had bought a flat in a project under construction by a simple written contract, and the seller transferred it to someone else before delivery:

Court of Cassation Assembly of Civil Chambers Decision
Assembly of Civil Chambers, E. 2024/421, K. 2025/381, 18.06.2025 (the Assembly’s reasoning; who may invoke invalidity)

“It must therefore be accepted that only the consumer may invoke the invalidity, for breach of form, of pre-paid home sale contracts made in simple written form.” (unofficial translation)

Court of Cassation Assembly of Civil Chambers Decision

“Although under the general provisions referred to above the sanction for breach of official form is absolute nullity, since article 41/1 of Law No. 6502 prohibits the seller from subsequently invoking the invalidity of the contract to the detriment of the consumer, it must be accepted that the consumer may claim registration where the conditions in that article are met.” (unofficial translation)

The 3rd Civil Chamber decision on penalties and lost rent concerns a promise to sell made under the former Code of Obligations No. 818; the Chamber also gave the corresponding provisions of Law No. 6098:

Court of Cassation Decision
3rd Civil Chamber, E. 2023/3369, K. 2024/1842, 05.06.2024 (the Chamber’s reasoning for reversal; reservation of the penalty)

“If the right to demand performance of the penalty has been reserved by contract or by notice given up to the time of performance, the penalty may be claimed even after performance.” (unofficial translation)

Court of Cassation Decision

“Although the claimant sought the lost-rent receivable suffered because of the delay together with the penalty cumulative with performance, compensation for lost rent and the penalty cumulative with performance agreed in the contract cannot be claimed together.” (unofficial translation)

Court of Cassation Decision

“This formal notice sent by the claimant to the defendant demanding payment of the penalty has the character of a reservation of rights.” (unofficial translation)

Court of Cassation Decision
6th Civil Chamber, E. 2026/23, K. 2026/496, 12.02.2026 (resolution of conflicting rulings of regional courts of appeal)

“Accordingly, under Law No. 6306, the owner of an independent unit of residential character in a main property with risky-structure status is a consumer under the urban transformation legislation, the flat-for-land construction contract made with the contractor on that basis and Law No. 6502 on Consumer Protection, and consumer courts have jurisdiction to resolve the dispute.” (unofficial translation)

In an action against the seller and the bank that granted a linked loan for a home that was not delivered, the 3rd Civil Chamber corrected the start date of advance interest:

Court of Cassation Decision
3rd Civil Chamber, E. 2023/4347, K. 2024/3439, 31.10.2024 (the Chamber’s reasoning for upholding as corrected)

“whereas, being bound by the claim, it should have been decided that TRY 220,915.00 be collected from the defendants and paid to the claimant together with advance interest from the date of each payment” (unofficial translation)

Court of Cassation Decision
3rd Civil Chamber, E. 2025/1709, K. 2025/4986, 20.10.2025 (the Chamber’s reasoning for upholding; pre-paid sale in simple written form)

“that the invalidity of the pre-paid sale contract cannot be invoked to the detriment of the consumer, that in the flat sale contract dated 01.04.2021 concluded between the parties, whose signature is not denied, … it is established within the scope of the contract that the claimant made an advance payment of TRY 275,000.00” (unofficial translation)

The Assembly decision is final. A search of Court of Cassation decisions since 2021 found no Assembly decision overturning or contradicting these decisions.

Practical Points

  • Documents: ask for the information form, building permit date, unit plan and specification list before signing.
  • Form: ask for the contract to be made at the land registry or before a notary; under a simple written contract the seller cannot invoke invalidity against you, but formalisation and an annotation protect you against third parties.
  • Payments: pay into the bank account stated in the contract and obtain the document for the security arrangement.
  • Time limits: count the withdrawal and rescission periods from the contract date and give notices through a notary; with a linked loan, watch the one-year period against the bank.
  • Late delivery: demand the penalty by formal notice before delivery or have a reservation written into the handover report; the penalty and lost rent cannot be claimed together; loss exceeding the penalty requires proof of the seller’s fault.
  • For sellers: sales without a building permit are prohibited and no payment or promissory note may be requested without a valid contract; the validity of unilateral extension and price-adjustment clauses is assessed separately in a dispute.

Frequently Asked Questions

Is a turnkey home sale contract in Türkiye invalid if it is not made at the land registry or before a notary?

Where the seller acts for commercial purposes and the buyer is a consumer, the contract is a pre-paid home sale; if the form is not met, the seller cannot invoke invalidity against the consumer (Law No. 6502 art. 41). According to the Assembly of Civil Chambers, only the consumer may rely on the lack of form, and the consumer may also claim registration if the conditions are met.

What is the maximum delivery period for a turnkey home in a pre-paid home sale in Türkiye?

The home must be delivered within the contractual period, which may not exceed forty-eight months from the contract date (Law No. 6502 art. 44). For older contracts, the text in force on the contract date should be checked.

Can both a penalty and lost rent be claimed if a turnkey home in Türkiye is delivered late?

No. According to the 3rd Civil Chamber of the Court of Cassation, a penalty cumulative with performance and compensation for lost rent cannot be claimed together; a loss exceeding the penalty may be claimed only if the seller’s fault is proved. The right to the penalty must be reserved until delivery.

Until when can a consumer withdraw from or rescind a pre-paid home sale contract in Türkiye?

The consumer may withdraw without reason within fourteen days of the contract. Law No. 6502 art. 45 also grants a right of rescission without reason for up to twenty-four months; the seller may then claim costs and compensation of two to eight per cent of the price.

Is the bank also liable if a turnkey home bought with a loan in Türkiye is not delivered?

Yes, if the loan is a linked loan; the bank is then liable together with the seller, limited to the loan amount and for one year from the contractual delivery date where the home is not delivered (Law No. 6502 art. 35).

Is mediation mandatory in disputes arising from a turnkey home sale in Türkiye?

For monetary claims such as late-delivery damages, a penalty or a refund, applying to a mediator first is a precondition to suit. Disputes arising from rights in rem over real estate, such as annulment of title and registration, and disputes within the consumer arbitration committee’s jurisdiction are excluded (Law No. 6502 art. 73/A).

Related Articles

This article is for general information purposes only and does not constitute legal advice. Statutory texts are taken from the Official Legislation Information System and decisions from the official case-law database. The decisions cited are not cases handled by the firm.

Author:

If you have a question on this topic

This article was written by Av. Bayram Can Çapar. At Av. Bayram Can Çapar · ÇAPAR Hukuk, we provide legal services with our team in Denizli, İzmir, Aydın, Muğla, Manisa, Uşak, Afyonkarahisar, Kütahya, İstanbul and Ankara, Türkiye.

+90 258 241 55 54 · info@capar.av.tr · Send a message

Other articles in Real Estate Law

All Real Estate Law articles →

Cite as: Av. Bayram Can Çapar, “Turnkey Home Purchases in Türkiye: Off-Plan Sale Contracts, Late Delivery, Withdrawal and Title”, ÇAPAR Hukuk, 2026-11-19, https://capar.av.tr/en/article/turnkey-home-purchase-off-plan-sale-contract-turkiye

← All articles