Published · 22 min read

Last reviewed:

Expropriation and Easements in Geothermal Resource Areas in Türkiye: The Landowner's Rights

Text sizeTheme

Short answer: Under Turkish law, a geothermal licence holder first enters privately owned land by agreement with (with the permission of) the owner. If no agreement is reached, the licence holder cannot expropriate the land itself; it applies to the administration (in metropolitan cities the Investment Monitoring and Coordination Directorate, in other provinces the special provincial administration), and the administration adopts a public interest decision if it finds the request appropriate (Law No. 5686 art. 12). During the exploration licence stage only an easement may be requested; expropriation, and urgent expropriation as a special form of it, is possible only during the operating licence period and only for necessary places such as drilling sites, transmission lines and capture works. Relying on this distinction, the Council of State 6th Chamber annulled an urgent expropriation decision issued at the exploration licence stage, and the Council of State Assembly of Administrative Law Chambers dismissed the appeal and upheld the annulment. The proceedings are conducted under the Expropriation Law No. 2942, and the licence holder pays the compensation. For an easement, the compensation is the loss in value of the property; in a partial expropriation, the loss in value of the remaining part is added. An action for annulment of the expropriation must be filed before the administrative courts within thirty days of the court’s notification; the compensation itself is determined by the civil court of first instance. For an urgent expropriation decision, the starting point of the time limit is assessed separately.

This article explains Turkish law. It is an English translation of the Turkish original; in case of any discrepancy, the Turkish text prevails.

In brief

Under Turkish law, a geothermal licence holder gains access to land by agreement, easement, expropriation or urgent expropriation, and only an easement may be requested under an exploration licence. The owner's rights to compensation, easement compensation, the remaining part and court actions under Laws No. 5686 and 2942, with Council of State and Court of Cassation decisions.

Under Turkish law: what a landowner should know when geothermal drilling, a pipeline or a facility affects their field or land — the special easement and expropriation regime of Law No. 5686, the distinction between exploration and operating licences, urgent expropriation, how compensation is calculated, the available court actions and the restrictions in resource protection zones.

What Are Expropriation and Easements in Geothermal Areas? The Special Statutory Regime

In Türkiye, the exploration and operation of geothermal resources are governed by the Geothermal Resources and Natural Mineral Waters Law No. 5686. The resource often lies beneath or near privately owned fields, vineyards or orchards; drilling a well, laying the pipeline that carries the fluid or building capture works requires access to the land on the surface. This concerns owners of agricultural land; the rules described below are the same throughout the country.

Under the general expropriation regime, the administration that carries out a public service expropriates for its own needs (see Expropriation and the Owner’s Rights). In the geothermal context, however, the party that needs the land is the licence holder, which is usually a private company. The Law therefore establishes a separate regime: the licence holder applies to the administration, the administration adopts the public interest decision, the proceedings follow Law No. 2942, and the licence holder pays the compensation and costs. Article 12 of the Law is the basis of this regime.

Statutory Provision — Geothermal Resources and Natural Mineral Waters Law (Law No. 5686) art. 12(1)-(4) (Easement and expropriation) (unofficial translation)

“(1) Where the holder of an exploration licence cannot reach agreement with the owner of privately owned immovable property in the area where exploration activities will be carried out, it may apply to the administration and request an easement.

(2) During the operating licence, where agreement cannot be reached with the owner of the immovable property only for necessary places such as drilling sites, transmission lines and capture works, the licence holder may apply to the administration and request expropriation or an easement. If the request is found appropriate after being examined and assessed by the administration, a public interest decision is adopted.

(3) Easement and expropriation proceedings are conducted in accordance with the Expropriation Law No. 2942 of 4/11/1983. Easement and expropriation compensation and costs are paid by the licence holder.

(4) The expropriated immovable property is registered in the land registry in the name of the administration and allocated to the licence holder for as long as the activities continue.”

The word “administration” in the Law is explained in the definitions article. Following a 2020 amendment, this function was given to the Investment Monitoring and Coordination Directorates (YİKOB) in metropolitan cities; in provinces without a metropolitan municipality, the special provincial administration is competent.

Statutory Provision — Geothermal Resources and Natural Mineral Waters Law (Law No. 5686) art. 3(1)(4) (Definitions) (unofficial translation)

“Administration: the Investment Monitoring and Coordination Directorates in metropolitan cities and, in provinces without a metropolitan municipality, the special provincial administrations,”

The implementing regulation adds pipelines to the necessary places during the operating period and requires the request to be decided within three months.

Regulatory Provision — Implementing Regulation of the Geothermal Resources and Natural Mineral Waters Law art. 22(2) (Easement and expropriation) (unofficial translation)

“The holder of an operating licence carries out operating activities during the licence, where applicable, with the permission of the owner of the privately owned immovable property. Where the licence holder cannot meet, by agreement with the owner, its need for immovable property for the places and routes required for drilling sites, transmission lines, … pipelines, capture works, facilities for the use of the fluid, etc. necessary for operation, it may apply to the Administration and request an easement or expropriation. The request is examined by the Administration and decided within three months at the latest. If the Administration finds the request appropriate, a public interest decision is adopted.”

Exploration Licence versus Operating Licence

For the owner, the first question is the type of licence. The Law provides for two periods:

  • Exploration licence period: If no agreement is reached, the licence holder may request only an easement (art. 12(1)). The Regulation expressly states that exploration in areas such as fields, vineyards and orchards is carried out with the owner’s permission (Regulation art. 22(1)).
  • Operating licence period: Expropriation or an easement may be requested only for necessary places such as drilling sites, transmission lines and capture works (art. 12(2)). The word “only” shows that expropriation is limited to the places needed for the activity, not the entire licence area.

The Council of State 6th Chamber applied this distinction in one case: since expropriation is not available at the exploration licence stage, urgent expropriation cannot be carried out at that stage either. The decision and its reasoning are set out below in the section “Geothermal Expropriation in Court Decisions”. Therefore, when you receive a public interest decision or an urgent expropriation decision, you should check which licence the measure is based on and whether an operating licence had been granted on the date of the measure.

How Does the Licence Holder Gain Access to the Land, and Who Expropriates?

Four routes emerge from the legislation:

  1. Agreement (permission): This is the primary route. The Regulation requires the owner’s permission in both the exploration and the operating periods. The price and terms of the agreement are set by the parties.
  2. Easement by way of expropriation: Ownership remains with the owner; an easement is established in favour of the administration over a specific part, the subsurface or the resource of the property. Pipeline routes are a typical example.
  3. Expropriation: Only during the operating licence period and only for necessary places. The property is registered in the name of the administration and allocated to the licence holder while the activity continues (art. 12(4)); ownership therefore does not pass to the company.
  4. Urgent expropriation: Possession of the property is taken after the value determined by the court is deposited in a bank, with the procedures other than valuation completed later (Law No. 2942 art. 27). The Regulation provides that, upon the licence holder’s application, the administration applies to the ministry to which it is attached (Regulation art. 22(3)). The Regulation still refers to the “Council of Ministers”; under the current Article 27 of Law No. 2942, the urgency decision is taken by the President.
Statutory Provision — Expropriation Law (Law No. 2942) art. 27(1) (Urgent expropriation) (unofficial translation)

“In the expropriation of immovable property required for national defence needs in the application of the National Defence Obligation Law No. 3634, or in cases where urgency is decided by the President, or in extraordinary situations provided for by special laws, possession of the immovable property may be taken, with the procedures other than valuation to be completed later, upon the request of the relevant administration, by depositing the value of the property determined by the court within seven days … in accordance with the principles of Article 10 by experts selected under Article 15, by the administration in the name of the owner … in the bank specified in the summons and notice issued under Article 10.”

What happens when the activity ends? If the administration determines that the expropriated property is no longer needed for the activity, the former owner is notified that the property will be returned on payment of its current market value; if the former owner does not wish to take it back within six months, the property remains with the administration (art. 12(5)). The Regulation also provides that the licence holder may not use the easement or expropriation area for other purposes and must vacate the area within the period stated in its project after restoring it to nature, failing which it is liable to compensate the damage in the area (Regulation art. 22(6), 22(7)).

If the licence holder has entered the land without any formal procedure, the owner may bring a de facto expropriation action (see De Facto Expropriation Claims in Türkiye). In a case where a geothermal pipeline had been laid, the Court of Cassation accepted that the power to expropriate belongs to the administration and that the company acted on behalf of the administration, and assessed against whom the action should be brought on that basis (decision below).

The Owner’s Rights: Compensation, Easement Compensation and Loss in Value of the Remaining Part

In geothermal expropriation, compensation is determined according to the general criteria of Law No. 2942. The expert panel takes into account the type of the property, its surface area, all qualities and elements that may affect its value and the value of each element separately, and, for agricultural land, the net income it would generate if used as it is (art. 11(1)). It is therefore important to ask that trees, buildings and elements affecting value such as irrigation be shown separately in the report. For details of the valuation criteria, see Expropriation Price Determination and Registration in Türkiye.

Easement compensation: The Law expressly states that, where an easement is established, the compensation is the loss in value arising in the property.

Statutory Provision — Expropriation Law (Law No. 2942) art. 11 (last paragraph) (Principles for determining expropriation compensation) (unofficial translation)

“Where an easement is established by way of expropriation, the loss in value that will arise in the immovable property or resource as a result of this expropriation shall be stated with its reasons. This loss in value is the expropriation compensation.”

The Court of Cassation 5th Civil Chamber finds it correct that, for an easement established for a pipeline, the rate of loss in value be determined by taking into account the nature of the property, its total surface area, its geometric shape and the route of the line. The decision concerns a general pipeline, not a geothermal one; however, since Law No. 5686 subjects the proceedings to Law No. 2942, it may be considered that the same criterion can apply to geothermal pipelines as well.

Court of Cassation Decision
5th Civil Chamber, E. 2024/2949, K. 2024/9299, 28.11.2024 (determining compensation for a pipeline easement)

“Valuing the property in the nature of agricultural land on the basis of its net income under Article 11(1)(f) of Law No. 2942, and determining the consideration for the permanent and temporary easement by stating the rate of loss in value, taking into account, under the last paragraph of Article 11 of the same Law, the nature of the immovable property, its total surface area, its geometric shape and the pipeline route, is correct.”

Loss in value of the remaining part: If part of a field is expropriated for a well site or a facility area, the loss in value arising in the remaining part is also added to the compensation. If the value of the remaining part increases because of the expropriation, the increase is deducted from the compensation; however, this deduction may not exceed fifty per cent of the expropriation compensation (art. 12(c)). If the remaining part has become unusable, the owner may request that the whole be expropriated.

Statutory Provision — Expropriation Law (Law No. 2942) art. 12 (Partial expropriation) (unofficial translation)

“b) Where the value of the part outside the expropriation decreases because of the expropriation, it is the amount found by determining the amount of the decrease and adding it to the expropriation compensation of the expropriated part determined in accordance with the principles in subparagraph (a).

… If the part remaining from a partially expropriated property is not in a usable condition, in cases where no action has been brought before the administrative courts against the expropriation, the expropriation of this part is also mandatory upon the owner’s written application made at the latest within thirty days of notification of the expropriation decision.”

Annulment Action versus Compensation Action: Which Court, Which Time Limit?

Two separate actions are heard before two separate courts:

  • Lawfulness of the measure (annulment action): The claim that the public interest decision, the expropriation or easement measure, or the urgent expropriation decision is unlawful is raised before the administrative courts. Grounds such as the expropriation being based on an exploration licence, or the public interest or urgency not being shown in concrete terms, are raised in this action. In the decisions cited in this article, actions against Presidential decisions on urgent expropriation were heard at first instance by the Council of State 6th Chamber, and the appeals were examined by the Council of State Assembly of Administrative Law Chambers.
  • Compensation (determination and registration action): If no agreement is reached through the purchase procedure, the administration applies to the civil court of first instance where the property is located and requests the determination of the compensation and the registration of the property or easement in its name (art. 10(1)). The owner must submit their defence and evidence in writing within ten days of service of the summons (art. 10(3)(h)). The registration judgment is final; the right of appeal and cassation regarding the compensation is reserved.
Statutory Provision — Expropriation Law (Law No. 2942) art. 14(1) (Right of action) (unofficial translation)

“Within thirty days from the date of the notification made by the court under Article 10 to the owner of the immovable property subject to expropriation, or, for those who could not be notified, from the date of the newspaper announcement made by the court in lieu of notification, an action for annulment may be brought before the administrative courts against the expropriation, and an action for correction may be brought before the ordinary courts against material errors.”

The court’s summons contains a warning that, if those who have brought an annulment action before the administrative courts fail to prove that they have done so, the expropriation will become final and the property will be registered in the name of the administration (art. 10(3)(f)). Filing the annulment action is therefore not enough; proof that it was filed must be submitted to the civil court of first instance. For the relationship between the annulment of an urgent expropriation decision and the compensation action, see Urgent Expropriation Annulment Does Not End Price Suit. The starting point of the time limit for challenging an urgent expropriation decision should be assessed separately according to the actual dates of notification and announcement; the sources examined for this article contain no provision specific to geothermal matters on this point.

Restrictions in Resource Protection Zones

Land that is not expropriated may still fall within the protection zone of a geothermal resource. The Law defines the protection zone as an area designated to protect the resource and the geothermal system against external factors, in which construction and land use may be restricted where necessary (art. 3(1)(14)). The licence holder commissions the protection zone study; the administration approves it after obtaining the opinion of MTA (the General Directorate of Mineral Research and Exploration). The restrictions envisaged in the study are reflected in zoning plans.

Statutory Provision — Geothermal Resources and Natural Mineral Waters Law (Law No. 5686) art. 14(2) (Protection of the resource reservoir) (unofficial translation)

“(2) Protection zone study reports are approved by the administration after obtaining the opinion of MTA. The restrictions and conditions regarding land use and construction envisaged in the resource protection zone study are taken as the basis in zoning plans. The general principles for the measures to be taken in resource protection zones are determined by regulation.”

The articles of Law No. 5686 examined for this article contain no separate compensation rule for protection zone restrictions. The route of challenge against the zoning plan or act introducing the restriction should be assessed separately.

Geothermal Expropriation in Court Decisions

No urgent expropriation under an exploration licence. In a geothermal exploration licence area, an urgent expropriation decision issued for an access road to a drilling well and for pipelines was annulled by the Council of State 6th Chamber with respect to one owner’s parcel; the Assembly of Administrative Law Chambers upheld the annulment. According to the Chamber’s reasoning:

Council of State Assembly of Administrative Law Chambers Decision (upheld reasoning of the Council of State 6th Chamber)

“at the exploration licence stage, where agreement cannot be reached with the owner of privately owned immovable property in the area subject to exploration, only an easement may be requested for the property; and, from an assessment of the provision in paragraph 2, it is clear that at the operating licence stage expropriation or an easement may be established for privately owned immovable property necessary for operating activities, … since recourse to expropriation under Law No. 2942 is not available for exploration activities at the exploration licence stage, urgent expropriation cannot be applied either…”

In this case the operating licence was granted after the urgent expropriation decision; the Council of State took as its basis the licence situation on the date of the measure.

Urgent expropriation may be upheld for a geothermal-based project. On the other hand, in an action against an urgent expropriation decision issued for a geothermal-heated greenhouse organised industrial zone, the Assembly of Administrative Law Chambers, while stressing that urgency is exceptional, concluded that urgency and public interest existed in the specific case and upheld the dismissal of the action. This decision concerns an expropriation based not on Article 12 of Law No. 5686 but on organised industrial zone legislation; it was adopted by majority vote.

Council of State Assembly of Administrative Law Chambers Decision

“Since urgent expropriation is an exceptional method, the conditions showing the existence of urgency must be set out beyond the grounds for ordinary expropriation. … in the specific case, it has been concluded that the state of urgency required for the application of Article 27 of Law No. 2942 and the public interest pursued by resorting to this method exist…”

Council of State Assembly of Administrative Law Chambers Decision (dissenting opinion)

“the reason that the geothermal-heated greenhouse project should be completed and put into operation as soon as possible is not, on its own, sufficient for the urgent expropriation of the properties in the area…”

Proper defendant where a pipeline is laid without expropriation. In an action to stop interference brought over a property on which the licence holder company had laid a geothermal pipeline, the Court of Cassation accepted that, under Law No. 5686, the power to expropriate belongs to the administration and that the company acted on behalf of that administration. Because the decision predates the 2020 amendment, it refers to the special provincial administration; today, in metropolitan cities, the administration is the YİKOB (art. 3(1)(4)).

Court of Cassation Decision

“given that an exploration and operating licence was granted … for laying a pipeline for the purpose of passing the geothermal energy transmission line at issue, and that under Law No. 5686 the competent and responsible administration is the Special Provincial Administration, … it being understood that in the act at issue the power to expropriate belongs to the Special Provincial Administration and that the company to which the case was notified acted on behalf of this administration…”

Practical Points

  • Find out the type and date of the licence. An urgent expropriation decision issued at the exploration licence stage was found unlawful by the Council of State 6th Chamber, and the Assembly of Administrative Law Chambers upheld the annulment; the Chamber took as its basis the licence situation on the date of the measure.
  • Question whether the requested area is a “necessary place”. During the operating period the Law limits expropriation to necessary places such as drilling sites, transmission lines and capture works; an area exceeding the need may be challenged.
  • If an easement is sufficient, ownership need not be taken. Under Article 4 of Law No. 2942, an easement may be established instead of taking ownership where it is sufficient for the purpose.
  • Do not miss the thirty-day time limit. The time limit for the annulment action is thirty days from the civil court’s notification; prove the filing of the action to that court.
  • Submit evidence within ten days in the compensation action. Raise elements such as trees, buildings, irrigation and the loss in value of the remaining part at the first stage.
  • If the remaining part is unusable, do not forget the written application. If no administrative action has been brought, the expropriation of the remaining part may also be requested within thirty days of notification.
  • Put the agreement in writing. Where access is by permission or agreement, write the price, the duration, the line route and the restoration of the area into the contract; the Regulation obliges the licence holder to restore the area to nature when leaving it.
  • Follow up your right of return. If the activity ends and the property is no longer needed, the offer of return must be answered within six months.

Frequently Asked Questions

Can a geothermal exploration licence holder expropriate my field under Turkish law?

No. Under Article 12 of Law No. 5686, if no agreement is reached with the owner during the exploration licence period, only an easement may be requested. The Council of State Assembly of Administrative Law Chambers upheld an annulment decision holding that, since expropriation is not possible at the exploration licence stage, urgent expropriation cannot be applied either. Expropriation is possible only during the operating licence period and for necessary places such as drilling sites, transmission lines and capture works.

Does a geothermal operating licence holder company in Türkiye expropriate my land itself?

No. The licence holder applies to the administration, which is the Investment Monitoring and Coordination Directorate in metropolitan cities and the special provincial administration in other provinces. If the request is found appropriate, the administration adopts the public interest decision and the proceedings follow the Expropriation Law No. 2942. The licence holder pays the compensation and costs. The expropriated property is registered in the name of the administration and allocated to the licence holder while the activity continues.

How is compensation calculated for an easement established for a geothermal pipeline in Türkiye?

The compensation for an easement is the loss in value that the easement causes to the property (Law No. 2942 art. 11, last paragraph). In a Court of Cassation 5th Civil Chamber decision on a non-geothermal pipeline, the agricultural land was valued on the basis of net income and the easement consideration was determined by stating the rate of loss in value; the rate was set by taking into account the nature of the property, its total surface area, its geometric shape and the route of the line.

When and where is an annulment action filed against a geothermal expropriation in Türkiye?

The annulment action is filed before the administrative courts within thirty days of the notification made by the civil court of first instance under Article 10 of Law No. 2942, or, for those who could not be notified, of the newspaper announcement (art. 14). Proof of filing must be submitted to the civil court; otherwise the expropriation becomes final. The compensation is determined by the civil court of first instance where the property is located, in the determination and registration action brought by the administration.

Is land expropriated for a geothermal activity in Türkiye returned to the former owner?

If the administration determines that the land is no longer needed for the activity, under Article 12(5) of Law No. 5686 the licence holder and the former owner are notified that the property will be returned to the former owner on payment of its current market value determined under the procedure of the Expropriation Law. If the former owner does not wish to take it back within six months, the property remains with the administration.

Related Articles

This article is for general information purposes only and does not constitute legal advice. Statutory texts are taken from the Official Legislation Information System and decisions from the official case-law database. The decisions cited are not cases handled by the firm.

Author:

If you have a question on this topic

This article was written by Av. Bayram Can Çapar. At Av. Bayram Can Çapar · ÇAPAR Hukuk, we provide legal services with our team in Denizli, İzmir, Aydın, Muğla, Manisa, Uşak, Afyonkarahisar, Kütahya, İstanbul and Ankara, Türkiye.

+90 258 241 55 54 · info@capar.av.tr · Send a message

Other articles in Real Estate Law

All Real Estate Law articles →

Cite as: Av. Bayram Can Çapar, “Expropriation and Easements in Geothermal Resource Areas in Türkiye: The Landowner's Rights”, ÇAPAR Hukuk, 2026-11-14, https://capar.av.tr/en/article/geothermal-expropriation-easement-landowner-turkiye